Norynta Hardware
Lead times too long? We find who can ship sooner.
Send your spec. Within 48 hours you get makers worldwide with earlier slots, their lead time and where they are: transformers, switchgear, generators, AI hardware, aerospace and space parts, machinery, drone and robot parts. Free to ask.
Lead times right now
Typical waits at the big makers in 2026, from public sources. Ranges vary by spec.
| Large power transformers | 128-160 weeks |
|---|---|
| Medium-voltage switchgear | 66-104 weeks |
| Diesel generators over 3 MW | 100-110 weeks |
| Enterprise DRAM, large orders | 40-45 weeks |
Can't wait? Ask for refurbished or surplus units that ship sooner.
How it works
- Send your spec. Part or equipment, key specs, quantity, delivery country and the date you need it.
- Get makers with earlier slots. Within 48 hours: who can ship sooner, their lead time and where they are.
- Decide. You compare the options. Asking is free.